Map your own schedule export onto 3 tables and refresh: 8 DAX measures compute CPI, SPI, Cost Variance, EAC and VAC across 3 report pages and 17 visuals. The file carries no data — yours goes in. Publishing the result to a team needs a Power BI Pro seat at Microsoft's list price of US$14 per user per month (US$168 per user per year), so the earned-value maths behind the numbers your board sees has to be right before you share it.
DAX: DIVIDE(SUM('Tasks'[BCWP Earned Value]), SUM('Tasks'[ACWP Actual Cost]))
Uses: 'Tasks'[BCWP Earned Value], 'Tasks'[ACWP Actual Cost]
Format: 0.00
DAX: DIVIDE(SUM('Tasks'[BCWP Earned Value]), SUM('Tasks'[BCWS Planned Value]))
Uses: 'Tasks'[BCWP Earned Value], 'Tasks'[BCWS Planned Value]
Format: 0.00
DAX: SUM('Tasks'[BCWP Earned Value]) - SUM('Tasks'[ACWP Actual Cost])
Uses: 'Tasks'[BCWP Earned Value], 'Tasks'[ACWP Actual Cost]
Format: #,##0
DAX: DIVIDE(SUM('Tasks'[Baseline Cost]) * SUM('Tasks'[ACWP Actual Cost]), SUM('Tasks'[BCWP Earned Value]))
Uses: 'Tasks'[Baseline Cost], 'Tasks'[ACWP Actual Cost], 'Tasks'[BCWP Earned Value]
Format: #,##0
DAX: SUM('Tasks'[Baseline Cost]) - DIVIDE(SUM('Tasks'[Baseline Cost]) * SUM('Tasks'[ACWP Actual Cost]), SUM('Tasks'[BCWP Earned Value]))
Uses: 'Tasks'[Baseline Cost], 'Tasks'[ACWP Actual Cost], 'Tasks'[BCWP Earned Value]
Format: #,##0
DAX: AVERAGE('Milestones'[Slip Days])
Uses: 'Milestones'[Slip Days]
Format: 0.0
DAX: COUNTROWS('Issues')
Format: 0
DAX: AVERAGE('Issues'[Days Open])
Uses: 'Issues'[Days Open]
Format: 0.0
| Column | Type | Summarize by |
|---|---|---|
Project Name | string | |
Task Name | string | |
Phase | string | |
Status | string | |
Finish | dateTime | |
Percent Complete | double | |
Baseline Cost | decimal | |
BCWS Planned Value | decimal | |
BCWP Earned Value | decimal | |
ACWP Actual Cost | decimal |
Header row: Project Name,Task Name,Phase,Status,Finish,Percent Complete,Baseline Cost,BCWS Planned Value,BCWP Earned Value,ACWP Actual Cost
| Column | Type | Summarize by |
|---|---|---|
Project Name | string | |
Milestone Name | string | |
Owner | string | |
Baseline Date | dateTime | |
Forecast Date | dateTime | |
Slip Days | int64 |
Header row: Project Name,Milestone Name,Owner,Baseline Date,Forecast Date,Slip Days
| Column | Type | Summarize by |
|---|---|---|
Project Name | string | |
Issue Key | string | |
Summary | string | |
Priority | string | |
Status | string | |
Created | dateTime | |
Days Open | int64 |
Header row: Project Name,Issue Key,Summary,Priority,Status,Created,Days Open
This page is the working piece. The full pack has everything below.